19 ice rinks, field houses, sports complexes, parks, trails and courts that are proposed, approved, under construction, newly open or recently lost across Castle Rock, Lone Tree, Parker, Highlands Ranch, Castle Pines and the county. Every entry comes from the town, county, district or operator building it, with the record linked under each one.

By Connor Tien, DougCo Social · Updated November 23, 2026

Castle Rock is building a sports center, talking to an ice rink operator and funding a field house, all at once. The County is planning a $100 million complex up by Sterling Ranch. Parker, Lone Tree and Castle Pines each have a park under construction. Those stories were scattered across our news section and the bigger development tracker, so here they are in one place, sports and recreation only.

Tracked
19 projects, 5 under construction
Biggest ticket
Zebulon, up to $100 million
Next vote
Nov. 24, 2026: Zebulon financing
Newest opening
Life Time Castle Pines, now open
Next due

How to read the labels. Proposed means a plan is in front of a town or the county with no binding approval yet (IceX is a letter of intent, nothing more). Approved means the money or the plan cleared its votes but nobody has confirmed dirt moving on the facility itself. Under construction and open mean what they say, per the agency or operator. Closed is the one we lost. Right now that is 3 open, 5 under construction, 7 approved, 3 proposed and 1 closed.

Dollar figures and dates come only from the record linked under each entry. If a number is not published by the town, county, district or operator, it is not on this page. Statuses change, so confirm with the agency before you plan around one. Know a sports or rec project I am missing? [email protected].

Castle Rock

The west side has the two biggest ones: the Town-owned sports center going up at the Brickyard, and Dawson Trails, where a field house and a proposed two-sheet ice rink sit on neighboring parcels along Dawson Trails Boulevard. Downtown lost its seasonal rink along the way.

The records

Castle Rock Sports Center (the Brickyard)

Under construction · Recreation center · Castle Rock

An approximately 145,177 sq ft Town-owned recreation facility on a 10.36-acre parcel inside the Brickyard, the former Acme Brick site. CD-Acme, the Brickyard developer, manages construction under a guaranteed maximum price contract with Saunders Construction, to plans by Barker Rinker Seacat, the architect the Town first hired for a 2022 feasibility study of a rec center on the Acme site. The Parks and Recreation Commission’s Nov. 18, 2026 agenda carried a recreation center update and tour. The Town has not published an opening date in any record read for this page; its construction administration contract with the architect runs through Dec. 31, 2027.

Cost and who pays: The Town is financing up to $75.5 million through certificates of participation (maximum total repayment $155 million, maximum annual payment $7.4 million), plus about $7.9 million the Town advances for parking and infrastructure on the site.

Last official action: Aug. 18, 2026: Town Council approved the first amendment to the architect’s construction administration contract (RES 2026-089, up to $1,086,302, through Dec. 31, 2027). Nov. 18, 2026: Parks and Recreation Commission update and tour.

Our Brickyard story · Source: Town of Castle Rock, ORD 2025-021 financing ordinance (June 17, 2025) and RES 2025-068 Rec Center Agreement (June 3, 2025)

IceX hockey and ice sports facility, Dawson Trails

Proposed · Ice rink · Castle Rock

A roughly 111,000 sq ft facility with at least two ice sheets on about 19 acres of Town-owned land in Dawson Trails. Phase 1 is expected to include two NHL-regulation sheets with spectator seating at one, sports medicine, athlete performance training and an athlete-focused school; a possible second phase adds more ice and a hotel. Town Council approved a non-binding letter of intent on Nov. 17, 2026, which starts negotiations and nothing more; the land and any money still need separate Council votes. On the LOI’s site map (Exhibit A), the 19-acre rink parcel sits right next to the 23.6-acre Gold Crown field house property on the west side of Dawson Trails Boulevard, separated only by a 1.5-acre public right-of-way at the Ike Street roundabout. The Town would build Ike Street south of the boulevard for access.

Cost and who pays: Proposed Town contributions in the LOI: the land; up to $2.3 million in reimbursed development, impact and permit fees and construction use tax; up to $3 million toward horizontal construction; $500,000 a year for 10 years under a resident services agreement; and a sales tax share-back on sales at the facility of 4.0% of the Town’s 4.2% rate for the first five years and 2.0% for years six through ten, capped at $3 million over the ten years.

Opening target: Targeted for Q4 2028 to Q1 2029, with Phase 1 operational by August 2029, per the LOI, subject to approvals, utilities and financing.

Last official action: Nov. 17, 2026: Town Council approved RES 2026-134, authorizing the Mayor to sign the non-binding LOI, which stays in effect through Dec. 31, 2030 unless extended.

Full story · Source: Town of Castle Rock, RES 2026-134 (Nov. 17, 2026) and Exhibit 1, the LOI with Exhibits A to E

Gold Crown Field House, Dawson Trails

Approved · Field house · Castle Rock

An indoor court complex the Gold Crown Foundation will own and run on public land west of Dawson Trails Boulevard. The site development plan filed with the Town (SDP26-0014, status date Nov. 2, 2026) describes an 83,000 sq ft building in two phases on 24.52 acres: eight basketball and 16 volleyball courts in Phase 1, two more basketball and four more volleyball courts in Phase 2, plus two outdoor flag football fields and parking. The County’s records describe the smaller version it funded: the staff report says about 65,000 sq ft with six basketball courts, 12 overlapping volleyball courts and a multi-purpose room at an expected project cost of about $24 million, and the funding agreement itself says 68,000 sq ft with six basketball and nine overlapping volleyball courts, about $26 million in hard costs and a $35 million total project budget. The plan has grown since the money was approved. Per that agreement, construction is expected to start in the first quarter of 2027, timed with the Crystal Valley interchange, with a planned opening in the second quarter of 2028. Funding is approved; the Town’s site plan record is on file with a status of Paid Online.

Cost and who pays: Douglas County: $7.5 million from the Parks, Trails, Historic Resources and Open Space sales tax, paid in two $3,750,000 installments, the first within ten days of Castle Rock issuing a building permit and no earlier than Oct. 1, 2026. Town of Castle Rock: the land, plus a waiver of up to $1 million in development impact and land use fees. The Foundation raises the rest.

Opening target: Second quarter of 2028, with construction starting in the first quarter of 2027, per the County funding agreement.

Last official action: Aug. 4, 2026: County commissioners adopted the $7.5 million parks funding agreement. July 21, 2026: Castle Rock Town Council approved the three-party funding agreement (RES 2026-081) and the fee waiver (RES 2026-082). Nov. 2, 2026: last update on the Town’s site plan record (status Paid Online).

Full story · Source: Town of Castle Rock development activity map, SDP26-0014; Douglas County, Aug. 4, 2026 release, staff report and funding agreement

The Challenge Hill stairs climbing the ridge at Philip S. Miller Park in Castle Rock, the west end of the Industrial Tributary Trail

Industrial Tributary Trail

Approved · Trail · Castle Rock

The east-west trail that ties downtown Castle Rock to Philip S. Miller Park, running past the sports center and the Brickyard. Wilson & Company holds the design contract, now up to $1,288,039 and extended to April 30, 2027. In October 2026 the Town approved a construction and maintenance agreement with BNSF Railway for the trail’s rail crossing work and a cost-participation agreement under which CD-Acme builds additional trail improvements alongside the Brickyard and the Town reimburses eligible costs. The Parks and Recreation Commission got a project update on Oct. 21, 2026.

Cost and who pays: Town contribution to the developer-built trail improvements is estimated at up to $4,975,062.47 (RES 2026-122). Design services up to $1,288,039 (RES 2026-049).

Last official action: Oct. 20, 2026: Town Council consent calendar, RES 2026-121 (BNSF agreement) and RES 2026-122 (CD-Acme cost participation).

Full story · Source: Town of Castle Rock, RES 2026-122 (Oct. 20, 2026) and RES 2026-049 (April 21, 2026)

Rink at the Rock (downtown)

Closed · Ice rink (lost) · Castle Rock

The seasonal outdoor rink at the northeast corner of Perry and Fourth is the one downtown lost. The operator’s own site listed Feb. 20, 2023 as the last day of skating, and the Town’s FAQ, posted Aug. 28, 2023, says the current owner determined it was not possible to keep the rink and sold the shade structure. Before that, the Town approved demolition of the house at 414 N. Perry St., directly north of the rink pavilion, on Sept. 6, 2022, and the Design Review Board approved the Perry Street Social site plan for the lot (Lot 4A, Block 11) on Nov. 9, 2022, a plan that kept the pavilion for winter skating. What happened after that, who owns the corner now, and why the plan stalled is in our story.

Last official action: Aug. 28, 2023: Town FAQ posted saying the rink will not return to the site. Earlier: DRB 2022-016 (Nov. 9, 2022) and RES 2022-101 (Sept. 6, 2022).

Whatever happened to Rink at the Rock · Source: Town of Castle Rock FAQ, Aug. 28, 2023; The Rink at the Rock site, Feb. 9, 2023 (Internet Archive); RES 2022-101 and DRB 2022-016

Local tip: IceX is a letter of intent, not a deal. The land transfer and every dollar in it come back to Town Council as separate votes, so "Castle Rock is getting an ice rink" is still "Castle Rock is talking to an ice rink operator" until those pass.

Lone Tree

Lone Tree is building a regional park with a beer garden in the Lyric neighborhood at RidgeGate, and the County is adding a short trail link next to the RidgeGate Parkway light rail station.

The records

High Note Regional Park

Under construction · Regional park · Lone Tree

At the northwest corner of High Note Avenue and Lyric Street. The City and South Suburban Parks and Recreation broke ground on Phase 1 on April 29, 2026: two lit synthetic multipurpose fields, a playground, a dog park with separate big-dog and small-dog areas, a 200-seat beer garden (Lone Tree Brewing Company is the anticipated operator), a food truck area, a water play feature, community gathering space, the Happy Canyon Trail connection to Schweiger Ranch and the East West Trail, and parking. The City lists it as Active Construction.

Cost and who pays: About $31 million for Phase 1: South Suburban $13 million, City of Lone Tree $9 million, Douglas County $7.5 million, Southeast Public Improvement Metropolitan District $1 million, Great Outdoors Colorado $580,000.

Opening target: 2027, per the City.

Last official action: April 21, 2026: City Council approval (per the City’s project page). April 29, 2026: groundbreaking.

Full story · Source: City of Lone Tree, groundbreaking announcement and project page

Happy Canyon Creek Trail Connection

Approved · Trail · Lone Tree

An 800-foot, 10-foot-wide trail connection with a prefabricated bridge, south of RidgeGate Parkway on the east side of South Havana Street, next to the RidgeGate Parkway light rail station and the future Tall Tales Ranch. It links the Havana Street sidewalk to the Happy Canyon Creek Regional Trail on the east side of the creek. Douglas County awarded the construction contract to 53 Corporation, the lowest of ten bidders, with substantial completion due by Dec. 31, 2026.

Cost and who pays: $508,741 construction contract, funded by the State’s Strong Communities grant; total project funding including the grant and local match is $1,306,000. The bridge was a separate $215,150 contract in January 2026.

Last official action: March 24, 2026: County commissioners adopted the construction contract.

Source: Douglas County, construction contract and staff report (March 24, 2026)

Parker

Parker’s big one is Salisbury Regional Park, where the ballfields come first and the 17 pickleball courts wait on funding. The Town also lists a newly open community park and three more that developers will build.

The records

Salisbury Regional Park expansion

Under construction · Regional park · Parker

Phase 1 is underway through 2026: four lit grass baseball and softball fields, two lit synthetic turf multipurpose fields, a restroom and pavilion, parking, landscaping, utilities and updates to the existing ballfields. Phase 2 is being designed and depends on funding and bids: 17 lit pickleball courts, two lit tennis courts striped for four more pickleball courts, a community hub pavilion, an outdoor fitness area, an inclusive playground, a bike pump track and a bike skills course.

Cost and who pays: About $16.2 million for Phase 1: $8,710,539 in municipal shareback from Douglas County’s 2022 parks and open space sales tax, plus a $7.5 million grant awarded to the Town in 2025.

Last official action: March 9, 2026: Parker Parks and Recreation project update.

Full story · Source: Parker Parks and Recreation, March 9, 2026, and the Capital Projects page

Looking Glass Community Park

Open · Community park · Parker

A 25.70-acre developer-built park with a dog park, fields, playgrounds, four pickleball courts and a large central picnic pavilion. The Town lists it as open for public use; the developer maintains it for two years after the Town’s final acceptance, which the Town anticipated in January 2026.

Cost and who pays: Funded by the subdivision developer.

Last official action: Town acceptance anticipated January 2026, per the Capital Projects page.

Source: Parker Parks and Recreation, Capital Projects

Newlin Gulch Regional Trail connection

Under construction · Trail · Parker

A one-mile, ten-foot-wide regional trail connection linking regional trails, listed by the Town as under construction.

Last official action: Listed as under construction on the Town’s Capital Projects page, read Nov. 23, 2026.

Source: Parker Parks and Recreation, Capital Projects

Tanterra, Brandy Gulch and Oak Gulch community parks

Proposed · Community parks · Parker

Three developer-funded parks the Town lists as future projects with acceptance dates to be determined. Tanterra Community Park (31.36 acres): a multi-use field, four pickleball courts, a playground and a trike track. Brandy Gulch Community Park (24.14 acres): a natural grass multipurpose field, two basketball courts, a ninja warrior course, an asphalt bike pump track and a downhill bike park. Oak Gulch Community Park (14.86 acres): a natural grass ballfield and a nine-hole disc golf course.

Cost and who pays: Developer-funded.

Last official action: Listed as future projects on the Town’s Capital Projects page, read Nov. 23, 2026.

Source: Parker Parks and Recreation, Capital Projects

Local tip: Looking Glass Community Park is open now with four public pickleball courts, so you do not have to wait for Salisbury Phase 2 to play on something new in Parker.

Highlands Ranch

Highlands Ranch is unincorporated, so its land deals run through Douglas County and the HRCA. The one to watch is Wildcat Regional Park on the northeast side.

The records

Wildcat Regional Park trails

Approved · Regional park and trails · Highlands Ranch

Douglas County agreed at its Oct. 14, 2025 land use hearing to quitclaim the 202-acre Wildcat property in Highlands Ranch to the Highlands Ranch Community Association (announced Oct. 16). The HRCA has three years to build a walking and bike trail network with a trailhead on Wildcat and the adjoining open space, open to all Douglas County residents, not just HRCA members. The County’s November 2026 grant resolution puts the full network at roughly 12 miles of trail, with a first 0.85-mile multipurpose segment covered by a Colorado Parks and Wildlife grant request of up to $50,000.

Cost and who pays: $3.5 million from the County’s Parks, Trails, Historic Resources and Open Space sales tax for the land transfer; CPW and Great Outdoors Colorado grant requests for trail construction.

Last official action: Nov. 10, 2026: County commissioners adopted the resolution supporting the CPW Non-Motorized Trails grant application and completion of the Wildcat Regional Park Trail project.

Source: Douglas County, Oct. 16, 2025 release; County resolution of Nov. 10, 2026

Castle Pines

Castle Pines got its Life Time, is rebuilding Coyote Ridge Park, and has a 74-acre regional park on paper in The Canyons.

The records

The waterslides over the outdoor pool at Life Time Castle Pines

Life Time Castle Pines

Open · Athletic club · Castle Pines

Open at 7373 Canyon Forge Drive in The Canyons. Life Time’s own page reads Now Open (checked Nov. 23, 2026) and puts the club at more than 102,000 sq ft, with indoor and outdoor pickleball, pools including a lap pool, cold plunge, sauna, hydrotherapy, a Kids Academy, LifeCafe, LifeSpa and LifeClinic. Membership required. That is its outdoor lap pool in the photo at the top of this page, from our Nov. 12 walkthrough.

Last official action: Nov. 18, 2026: opening day, per our Life Time story; Life Time’s location page shows Now Open as of Nov. 23, 2026.

What it costs and what you get · Source: Life Time, Castle Pines location page

Coyote Ridge Park improvements

Under construction · Community park · Castle Pines

A rebuild of the City’s 40.5-acre park west of I-25, with an expansion of about 11 acres planned. Construction began Sept. 8, 2026: a new baseball field, an all-inclusive playground for all ages with poured-in-place or synthetic turf surfacing, accessible walks to the shade structures plus new ones, basketball court fencing, vault toilets, a plaza, a pollinator garden and bike racks. The City’s latest update has crews on the ballfield fencing and backstops, a new concrete trail poured from the playground and pavilions to Hidden Pointe Boulevard, and the lower playground lot closing Dec. 1 as the project moves to the playground phase.

Cost and who pays: Estimated at about $5 million, per the City.

Opening target: Spring 2027, per the City’s estimated completion.

Last official action: City project page update ahead of the Dec. 1, 2026 lower-playground closure.

Source: City of Castle Pines, Coyote Ridge Park Improvements

Soaring Hawk Park

Proposed · Regional park · Castle Pines

A 74-acre regional park east of I-25 in The Canyons, south of Rueter-Hess Reservoir. City Council adopted the concept plan on Aug. 27, 2024, as part of the 2024 Parks and Recreation Comprehensive Plan. A pool was not recommended for this site. No construction schedule or budget is published.

Last official action: Aug. 27, 2024: concept plan adopted by City Council.

Source: City of Castle Pines, Future Park Planning

The Canyons pickleball courts, Canyon Village

Open · Pickleball courts · Castle Pines

The Canyons lists pickleball courts at Canyon Village, its amenity center, among the community’s amenities, with a shade structure for breaks between games, next to the resort-style pool. These are community courts, not a public park.

Last official action: Listed on The Canyons’ amenities page, read Nov. 23, 2026.

Our Castle Pines pickleball story · Source: The Canyons, amenities page

Local tip: The lower playground lot at Coyote Ridge closes Dec. 1, 2026 as the rebuild moves to the playground phase, so park up top this winter.

Douglas County

The County’s own projects: the Zebulon complex up by Sterling Ranch, which the County plans to finance with certificates of participation (it says the parks sales tax is not expected to be the primary funding source), plus a trail park near Macanta and a new trailhead where the High Line Canal begins, both paid from the Parks, Trails, Historic Resources and Open Space sales tax voters extended in 2022.

The records

Zebulon Regional Sports Complex

Approved · Sports complex · Northwest Douglas County (Sterling Ranch area)

The County’s regional sports complex on 46.5 acres it received from Sterling Ranch on Oct. 14, 2025, within a 357-acre site that keeps 185 acres as open space. Proposed facilities, in the County’s own words, are proposed and may change: multiple ice rinks, multi-sport courts for basketball, volleyball and pickleball, baseball and softball fields, outdoor fields for soccer, lacrosse, football and rugby, a fitness center, golf simulators and an aquatic center with the county’s first 50-meter competition pool, in partnership with the Colorado Aquatics Foundation. KT Development is the development partner. The site is being graded and prepared for power, water and sewer now; construction of the sports facilities is expected to begin in 2027.

Cost and who pays: Up to $100 million for the complete project, per the County; KT Development has given a guaranteed maximum construction price of $65 million for the main sports facilities. Financed through certificates of participation, not a new tax. The resolution in front of commissioners on Nov. 24, 2026 caps the principal at $102 million, annual payments at $7.2 million and total repayment at $207 million, with a lease term no later than Dec. 31, 2056. Also on the Nov. 24 agenda: a $4,315,000 Phase 2 preconstruction and design agreement with KT Development and a $2,255,437 amendment to the site infrastructure agreement with SR Construction (on top of the $12,046,296 agreement from March 31, 2026).

Opening target: Late 2028, per the County’s Nov. 18, 2026 update.

Last official action: Nov. 10, 2026: commissioners adopted the Piper Sandler underwriting engagement letter for the COPs. Nov. 24, 2026: COP financing resolution, Phase 2 design-build agreement and infrastructure amendment on the commissioners’ 1:30pm business meeting agenda (item 3.b), with public comment.

Open house: support and concerns · Nov. 10 open house preview · March 2026 contracts vote · Source: Douglas County, Zebulon project pages (facilities, costs, development timeline) and Nov. 18, 2026 update; County COP authorizing resolution for Nov. 24, 2026

Macanta Regional Park

Approved · Regional park and trails · Unincorporated Douglas County, near Castle Rock

A 464-acre county park about one mile south of Crowfoot Valley Road and Pradera Parkway: 5.3 miles of trails, three sets of challenge stairs, a small playground and a trailhead with parking, shelters and restrooms. Commissioners approved the construction contract with Timberline Building Systems on Nov. 10, 2026, after approving a $113,050 steel pedestrian bridge from Wheeler Lumber on Nov. 3.

Cost and who pays: Construction contract up to $5.95 million (Timberline Building Systems); $113,050 for the pedestrian bridge; $191,445 to Architerra Group for final design and construction administration (April 28, 2026).

Opening target: June 2028, per the County.

Last official action: Nov. 10, 2026: commissioners adopted the construction contract.

Full story · Source: Douglas County, Nov. 12, 2026 release and the Nov. 10, 2026 contract record

High Line Canal Origins Trailhead

Approved · Trailhead · Unincorporated Douglas County (Waterton Road)

The small, informal parking lot where the High Line Canal meets Waterton Road, at 10401 Waterton Road, is being rebuilt by the High Line Canal Conservancy as a proper trailhead with interpretation about the canal where it emerges from Waterton Canyon. The County funds it from the parks sales tax; the Conservancy must finish by June 30, 2027.

Cost and who pays: $450,000 from Douglas County plus $150,000 in Conservancy matching funds, a $600,000 project.

Opening target: Completion required by June 30, 2027, under the funding agreement.

Last official action: Jan. 13, 2026: commissioners adopted the parks funding agreement.

Source: Douglas County, parks funding agreement with the High Line Canal Conservancy (Jan. 13, 2026)

Local tip: The Zebulon financing vote on Tuesday, Nov. 24, 2026 takes public comment at the commissioners’ business meeting. If you have an opinion on up to $102 million in certificates of participation, that is the room.

Frequently asked questions

Is Castle Rock getting an ice rink?

It is proposed, not approved. On Nov. 17, 2026, Castle Rock Town Council approved a non-binding letter of intent with IceX for a roughly 111,000 sq ft facility with two NHL-regulation ice sheets on about 19 Town-owned acres in Dawson Trails. The LOI targets an opening in Q4 2028 to Q1 2029, with Phase 1 operational by August 2029. The land transfer and any Town money still need separate Council approvals.

When does the Castle Rock Sports Center open?

The Town has not published an opening date in any record read for this page. The building is under construction at the Brickyard, the Parks and Recreation Commission’s Nov. 18, 2026 agenda carried an update and tour, and the Town’s construction administration contract with its architect runs through Dec. 31, 2027. Confirm the date with the Town before you plan around it.

What is Zebulon and when will it open?

Zebulon Regional Sports Complex is Douglas County’s planned 46.5-acre complex in the Sterling Ranch area of northwest Douglas County, with proposed ice rinks, indoor courts, ballfields, outdoor fields and an aquatic center with a 50-meter competition pool. The County puts the full project at up to $100 million, financed with certificates of participation rather than a new tax, and targets a late-2028 opening. Commissioners were scheduled to vote on the financing on Nov. 24, 2026.

Where are the new pickleball courts in Douglas County?

Open now: Life Time Castle Pines (indoor and outdoor courts, members only), Looking Glass Community Park in Parker (four public courts) and The Canyons’ community courts at Canyon Village in Castle Pines. Planned: 17 lit courts at Salisbury Regional Park in Parker in Phase 2, which depends on funding, and four more at Parker’s future Tanterra Community Park.

What happened to the downtown Castle Rock ice rink?

Rink at the Rock, the seasonal outdoor rink at Perry and Fourth, is gone. Its last day of skating was Feb. 20, 2023, per the operator’s site at the time, and the Town’s FAQ posted Aug. 28, 2023 says the owner determined it was not possible to keep the rink and sold the shade structure. The Perry Street Social plan the Design Review Board approved for the lot in November 2022 had kept the pavilion for skating. Our story on what happened to the corner is linked above.

Who pays for these projects?

The parks, trails and open space projects run on the Parks, Trails, Historic Resources and Open Space sales tax Douglas County voters extended in 2022, which funds the County’s own parks (Macanta, the Origins Trailhead) and its grants to the towns (Gold Crown, High Note, Salisbury, Wildcat). The two biggest buildings are financed differently: Castle Rock is funding its sports center with up to $75.5 million in certificates of participation, and the County plans up to $102 million in certificates of participation for Zebulon, which it says the parks tax is not expected to primarily fund. Life Time and The Canyons courts are private.

Sources

Where this page is checked, by jurisdiction. Each entry above also links its own record. Our own news pages are leads, never sources.

Get the groundbreakings and openings first

Council votes, ribbon cuttings and what's coming to your side of the county, in DougCo Drop and Castle Rock Crew. Join 16,100+ locals.

Subscribe Free