Castle Rock Council Approves IceX Ice Rink Talks in Dawson Trails

Castle Rock Town Council voted 7-0 on Nov. 17, 2026 to approve a non-binding letter of intent that starts talks with IceX on a 111,000-square-foot, two-sheet ice facility on about 19 Town-owned acres in Dawson Trails, with up to $13.3 million in proposed Town cash incentives.

By Connor Tien, DougCo Social·Published November 16, 2026·Updated November 19, 2026

Castle Rock Town Council voted 7-0 on Tuesday, Nov. 17, 2026, to approve a non-binding letter of intent that starts negotiations with IceX Foundation and IceX Castle Rock Management, LLC on a roughly 111,000-square-foot hockey and ice sports facility on about 19 acres of Town-owned land in Dawson Trails.

The resolution, RES 2026-134, authorizes the Mayor to sign the letter and Town staff to keep negotiating. Councilmember Kevin Bracken moved to approve it and Councilmember Tim Dietz seconded. Mayor Jason Gray, Mayor Pro Tem Laura Cavey and Councilmembers Ryan Hollingshead, Mark Davis and Max Brooks also voted yes. Per the staff report, final agreements and any binding financial or property commitments would come back to Council for separate approval.

What would be built

Per the letter of intent and the Town Manager's staff report:

  • Two NHL-regulation ice sheets, with spectator seats at one
  • Physical therapy and sports medicine, athlete performance training, and an athlete-focused school
  • Public skating, introductory recreation, youth and adult leagues, birthday parties, community events and a restaurant
  • A possible second phase with additional ice and a hotel

The staff report says the facility would respond to strong interest in an ice-skating rink in the Town's 2025 community survey.

What the Town would put in

Proposed Town contributionAmount
About 19 acres of Town-owned land in Dawson TrailsValued at about $9 million
Reimbursed development, impact and permit fees and construction use tax (Economic Development Fund)Up to $2.3 million
Reimbursed horizontal construction costs (General Fund reserves)Up to $3 million
Resident services agreement (General Fund)$500,000 a year for 10 years
Sales tax share-back on facility salesCapped at $3 million over 10 years
Building Ike Street for public accessTown estimate about $1 million

The four cash incentives add up to as much as $13.3 million. The sales tax share-back would return 4% of the Town's 4.2% sales tax on qualifying sales for the first five years after opening and 2% for years six through 10; the Town says its 0.2% public safety sales tax is excluded. The Town's Nov. 18 Council update says the resident services agreement's proposed benefits include 50% discounts on designated programs for Castle Rock residents, subject to eligibility and availability. The letter also allows overflow parking at the Dawson Trails park-and-ride for special events and a possible 4% public improvement fee on facility sales, subject to a separate agreement.

IceX would raise the rest of the money for what the staff report calls an approximately $40 million project, and would build, operate, maintain and program the facility.

Safeguards in the letter

  • The Town would keep a reversionary interest in the land if IceX doesn't build or operate the facility.
  • No land would transfer until IceX secures adequate funding under criteria set in final agreements.
  • Either side can terminate the letter at any time. It expires Dec. 31, 2030, unless extended.
  • All Town funding stays subject to annual Council appropriation, and the staff report says the project wouldn't affect Parks and Recreation initiatives already underway.

Timeline and public input

The staff report anticipates opening by 2029, subject to approvals, utilities and financing. The letter itself targets an opening between Q4 2028 and Q1 2029, with the first phase operational by August 2029. Within 90 days of signing, the two sides intend to swap first drafts of the property transfer, development and incentive, resident services and improvement fee agreements.

Public outreach planned in the staff report:

  • Open house: 4:30 to 6:30 p.m. Monday, Jan. 25, 2027, in Town Council Chambers at Town Hall, 100 N. Wilcox St.
  • Online: information at CRgov.com/IceX, with a feedback form open mid-December through late January

Dawson Trails is also where the Town says a Costco and a third Castle Rock King Soopers are under construction. Track every other project on our What's Being Built in Douglas County page and more on the town at our Castle Rock page.


Sources: Town of Castle Rock, RES 2026-134 legislation page, Town Manager's staff report and Exhibit 1, Non-Binding Letter of Intent (PDF), Nov. 17, 2026 Town Council agenda and roll-call vote; Town of Castle Rock, "Nov. 17 Council update," Nov. 18, 2026 (public safety tax exclusion, 50% resident discounts, open house location), checked Nov. 19, 2026.

Castle Rock · Town Council · Dawson Trails · ice rink · hockey

Frequently asked questions

Is Castle Rock getting an ice rink?

It's still a proposal. On Nov. 17, 2026, Town Council voted 7-0 to approve RES 2026-134, a non-binding letter of intent that lets the Mayor sign and Town staff start negotiating with IceX Foundation and IceX Castle Rock Management, LLC on a hockey and ice sports facility in Dawson Trails. Any land transfer or binding money would need further Council approval.

What would the IceX facility include?

About 111,000 square feet with two NHL-regulation ice sheets and spectator seats at one of them. Planned uses in the staff report include public skating, introductory recreation, youth and adult leagues, birthday parties, community events, a restaurant, sports medicine and performance training, and an athlete-focused school.

What would the Town contribute?

About 19 acres of Town-owned land in Dawson Trails, valued at about $9 million; up to $2.3 million in reimbursed fees and construction use tax; up to $3 million for horizontal construction costs; $500,000 a year for 10 years under a resident services agreement; and a sales tax share-back capped at $3 million. The Town would also build Ike Street for access, which staff estimates at $1 million.

When would it open?

The staff report anticipates opening by 2029, subject to approvals, utilities and financing. The letter of intent targets Q4 2028 to Q1 2029 for opening and expects the first phase to be operational by August 2029.

Will Castle Rock residents get a discount?

The proposed resident services agreement includes 50% discounts on designated programs, with eligibility, capacity limits and other details to be set in that agreement.

How can residents weigh in?

The staff report plans an open house from 4:30 to 6:30 p.m. Monday, Jan. 25, 2027. Information will be posted at CRgov.com/IceX, with an online feedback form open from mid-December through late January.

Castle Rock Crew · free weekly email

I send the new openings and what's changing in Castle Rock every Tuesday morning. No crime, no noise.

DougCo Social Experiences

We don’t just cover Douglas County — we get people together in it.

Small-group dinners and paint nights we host across the county. Come to one and you’re in.

See our experiences →

Get local news first

New openings, closings, and community updates delivered weekly. Join 16,100+ Douglas County locals.

Subscribe Free