Lone Tree Council Continues Hillcamp Access-Road Hearing to January

Lone Tree City Council held a public hearing Nov. 17, 2026 on the final plat for Hillcamp Trail, the road that would provide access to the proposed Hillcamp development on the bluffs south of the city, then continued it to Jan. 5, 2027. The Planning Commission had recommended approval with conditions on Oct. 13. Two related preliminary plans propose 343 single-family homes nearby; both remain on second referral with no hearing dates set.

By Connor Tien, DougCo Social·Published November 19, 2026

Lone Tree City Council continued a public hearing on part of the proposed Hillcamp development to Jan. 5, 2027, after hearing testimony for the first time on the project's access road at its Nov. 17, 2026 meeting. No decision was made that night.

The application at that hearing, a final plat called Hillcamp Trail Filing No. 1 (case SB25-0014), would extend Cabela Drive south into a new public street, renamed Hillcamp Trail, to serve as the main access road into the proposed Hillcamp community on the bluffs south of the city. It also includes a grade-separated pedestrian bridge carrying the East West Regional Trail over the new road, dedicated public right-of-way, and tracts for retaining walls and other infrastructure.

The Planning Commission had already recommended approval of that final plat, with conditions, on Oct. 13, 2026. Per the City of Lone Tree's own project page, public testimony on the application was not invited until the Nov. 17 Council hearing, which the Council then continued to Jan. 5, 2027, at 5:30 p.m., at the Lone Tree Civic Center, 8527 Lone Tree Parkway.

What Hillcamp Is

Hillcamp is the name for a proposed development generally south of Cabela Drive, west of Interstate 25, and north of the East West Regional Trail, on land inside the RidgeGate Planned Development District (7th Amendment) and the Southridge Preserve Planned Development District. The city is reviewing four related applications for it concurrently, though it says each one "must be decided separately":

  • Hillcamp Sub-Area Plan (case RG24-0007): sets the development framework and standards the other applications must follow
  • RidgeGate Rural Residential Preliminary Plan (case SB25-0010): 261 single-family detached lots
  • Southridge Preserve Preliminary Plan (case SB25-0009): 82 single-family detached lots, on Parcels 4 and 5 of the Southridge Preserve Planned Development District
  • Final Plat, Hillcamp Trail Filing No. 1 (case SB25-0014): the access-road application heard Nov. 17

Together, the two preliminary plans propose 343 single-family lots. Both remain on second referral, with the first referral having closed Feb. 10, 2026 and a priority comment deadline of May 26, 2026. Planning Commission and City Council hearing dates for both are listed as "to be determined" on the city's project pages, as is the hearing schedule for the sub-area plan.

Background

CBS Colorado has reported that the developer behind Hillcamp is Brookfield Residential, and that the company held a meeting with concerned Surrey Ridge-area residents on Nov. 13 at the Lone Tree Hub. The City of Lone Tree's own project pages for the four applications don't name an applicant or developer, referring only to "the applicant," so that detail is not independently confirmed here.

What's Next

The continued Council hearing on the Hillcamp Trail final plat resumes Jan. 5, 2027. The two preliminary plans setting the home count, and the sub-area plan underpinning them, have no Planning Commission or Council hearing dates yet. Residents can comment on any of the applications through the city's online comment form linked from each project's page, or by contacting Chuck Darnell, the city's principal planner, at [email protected] or 720-509-1180.

For more on growth around Lone Tree, see our Douglas County development hub and our Lone Tree coverage.


Sources: City of Lone Tree project pages for Final Plat, Hillcamp Trail Filing No. 1 (case SB25-0014; Oct. 13, 2026 Planning Commission recommendation, Nov. 17, 2026 Council hearing and continuance to Jan. 5, 2027), RidgeGate Rural Residential Preliminary Plan (case SB25-0010; 261 lots), Hillcamp Southridge Preserve Preliminary Plan (case SB25-0009; 82 lots), and Hillcamp Sub-Area Plan (case RG24-0007). Background on the developer and the Nov. 13, 2026 resident meeting per CBS Colorado, not independently confirmed by the city's own pages. All city pages checked Nov. 19, 2026.

Frequently asked questions

What is Hillcamp?

Hillcamp is a proposed development on the bluffs south of Lone Tree, generally south of Cabela Drive, west of Interstate 25, and north of the East West Regional Trail. The City of Lone Tree is reviewing four related applications for it concurrently, though each must be decided separately: a sub-area plan, two preliminary plans covering a combined 343 single-family lots, and a final plat for the project's access road.

How many homes are proposed?

343 single-family detached lots across two preliminary plan applications, per the City of Lone Tree's own project pages: 261 lots under the RidgeGate Rural Residential Preliminary Plan (case SB25-0010) and 82 lots under the Southridge Preserve Preliminary Plan (case SB25-0009). Both remain on second referral, with Planning Commission and City Council hearing dates listed as 'to be determined.'

What happened at the Nov. 17 City Council hearing?

City Council held a public hearing on the final plat for Hillcamp Trail Filing No. 1 (case SB25-0014), the application that would extend Cabela Drive south as a new public street called Hillcamp Trail to serve as the development's main access road. Per the city's project page, public testimony was invited for the first time at that hearing, and the hearing was continued to Jan. 5, 2027 at 5:30 p.m., at the Lone Tree Civic Center. No decision was made Nov. 17.

Did the Planning Commission already weigh in?

Yes. The Planning Commission recommended approval of the Hillcamp Trail final plat, with conditions, on Oct. 13, 2026.

What else is included in the access-road application?

Besides the new public street, the final plat includes a grade-separated pedestrian bridge carrying the East West Regional Trail over Hillcamp Trail, plus dedicated public right-of-way and tracts for retaining walls and other infrastructure.

How can residents comment on the project?

Through the city's online comment form for the application (linked from each project's page on cityoflonetree.com), or by contacting Chuck Darnell, the city's principal planner, at [email protected] or 720-509-1180. The priority deadline for comments to be included in the hearing agenda packet was May 26, 2026; later comments are entered into the public record at the hearing itself.

What's next?

The City Council hearing on the Hillcamp Trail final plat resumes Jan. 5, 2027. The two preliminary plans covering the 343 homes, and the sub-area plan that sets the framework for them, remain on second referral with no Planning Commission or Council hearing dates yet scheduled. The city's project pages say each of the four applications must be decided separately.

DougCo Drop · free weekly email

I send the new openings and what's changing in Douglas County every Thursday morning. No crime, no noise.

DougCo Social Experiences

We don’t just cover Douglas County — we get people together in it.

Small-group dinners and paint nights we host across the county. Come to one and you’re in.

See our experiences →

Get local news first

New openings, closings, and community updates delivered weekly. Join 16,100+ Douglas County locals.

Subscribe Free